The target for full completion is Mar 2019 — states are counting their work separately which makes tracking hard. Under PMGSY-I, 178,184 unconnected habitations were identified. So far up to 24/11/15, 112,550 habitations have been connected with PMGSY roads. http://pib.nic.in/newsite/PrintRelease.aspx?relid=131846

Update 15/12/2017: What's left of PMGSY-1?
----------------------------------------
The final 65,634 connections are expected to be done in 3.4 years from 24/11/15 to Mar 2019. At 15/12/17 145, 594 habitations were connected (130,974 + 14,620). From 24/11/15 to 15/12/17 in 2.06 years, 33,044 were added, at 16,060 pa. Left 1.233 yrs to connect 32,590 habitations.
http://pib.nic.in/newsite/PrintRelease.aspx?relid=174360

Update 16/04/2018: Target completion of PMGSY?
--------------------------------------------------
152,124 habitations are connected, equivalent to 85.37% of eligible habitations. 16,380 habitations connected by the States. What is left: 26,060 in less than one year.
http://pib.nic.in/newsite/PrintRelease.aspx?relid=131846

PMGSY Updated: 6/8/2018: Target for FY18 was 15,000 (22.85% of 65,634). 11,588 villages were connected. Target for FY19 is 19,725!
http://pib.gov.in/PressReleseDetail.aspx?PRID=1542248

Years Total PMGSY Total State Habitations
per PIB date New PMGSYs
————————————————————————
Till FY 14 97,838 (see pib 2017)
FY 15 109,136 11,298
FY 16 119,172 10,036
FY 17 131,077? 11,905
FY 18 142,665? 14,620 11,588
from http://omms.nic.in/Home/CitizenPage/

Change in last 3 years to 2016/7
⤞ Time for contract completion: 1 year —► 1/3rd year
⤞ Road km pa completed: 25,300 —► 47,400
⤞ Habitations pa connected: 6,530 —► 11,600
⤞ Funds (2 yrs average): Rs 9,200 cr —► Rs 18,600 cr ♪
♪ together with States contribution, funding is Rs 27,000 cr.

Progress in 2017/18 compared to previous 3 years
⤞ Road km pa completed: 47,400 —► 48,750
⤞ Habitations pa connected: 11,600 —► 11,909

PMGSY
PMGSY is for new connectivity and upgradation works. From time to time, Govt has broadened the scope, increased quality and added maintenance obligations. In FY 18 budget, it promised to connect habitations of 100 people in left-wing affected areas. Rural roads program sets out to create large, inter-connected village communities where people commute, micro-enterprises can flourish and farm produce and other goods are easily accessed. New opportunities arise, eg. private sector can add proper linkages from farm to markets via local pickup points, cold-chain, storage & food processing units.

* A big jump in road length constructed from 36,449km in 2015-16 to 47,447km in 2016-17
* A big jump in funding in Budget 2016-17, due to changed funding, from 100% from Centre to 60% (except for NE region). Centre spent Rs 19,000cr, while States spent Rs 8,000cr and did their own construction.

3 years of Modi govt: Rural roads take 124 days to build from UPA's 474